Birmingham Northern Beltline - Better Beltline









Monthly Construction & Environmental Project Updates

April 2015

West End (SR 79)


Environmental Status this reporting period
:

  • 12 Rain Days: 4/1 (0.49”), 4/3 (0.46”), 4/7 (0.33”), 4/10 (1.03”), 4/13 (0.59”), 4/14 (0.31”), 4/15 (0.20”), 4/17 (0.69”), 4/18 (0.58”), 4/20 (1.16”), 4/26 (1.75”), 4/29 (0.40”)
  • Total rainfall for April was approximately 8.00 inches
  • One temporary turbid discharge on April 28, 2015. ADEM notified and remedy initiated on April 28, 2015.


 