Birmingham Northern Beltline - Better Beltline






Monthly Construction & Environmental Project Updates

February 2015

West End (SR 79)

  • Utility work related to fiber optic lines and gas relocation work has resumed.
  • Jefferson County water line installation (under separate NPDES permit) ongoing near SR 79 and Green Drive. BMPs installed by Jefferson County contractor.
  • Tree clearing begun for Sediment Basin 5 on west side of SR79. BMPs in place.
  • Temporary Sedimentation basins 31 and 32 (with pumps and skimmers) on SR 79 functioning properly. Active stormwater treatment applied as necessary to discharge clean water.


Mainline (Station 2150 to Station 2235 at SR 75)   


Environmental Status this reporting period
:

  • 6 Rain Days: 2/2 (0.24”), 2/9 (0.06”), 2/17 (1.79”), 2/23 (1.28”), 2/24 (0.04”), 2/26 (0.55”), 2/28 (0.07”).
  • Total rainfall for February was approximately 4.5 inches
  • ADEM compliance inspection on 2/17/15: Minor deficiencies observed within two sediment control BMPs. No regulatory violations noted.
  • One water quality violation on 2/23/15: Temporary visible contrast between discharge and receiving water near station 2240.
  • Discharge reported to ADEM as corrections were implemented. Water quality clear on 2/24/15.


 