Birmingham Northern Beltline - Better Beltline









Monthly Construction & Environmental Project Updates

June 2015

West End (SR 79)

  • Utility work related to fiber optic lines and gas relocation work ongoing.
  • Jefferson County water line installation (under separate NPDES permit) completed near SR 79 and Green Drive. BMPs installed by Jefferson County contractor.
  • Sedimentation basin slopes on west side of SR79 stabilized with permanent seed and erosion control netting.
  • Sedimentation basin 4 area cleared with slopes stabilized with temporary seed/mulch.
  • Perimeter controls in place along stream to protect water quality.
  • Sediment Retention Barrier (silt fence and hay bales) remained on north and south sides of Self Creek.
  • Temporary Sedimentation basin 31, 32, and 33 (with pumps and skimmers) on SR 79 functioning properly. Active stormwater treatment applied as necessary to discharge clean water.


Mainline (Station 2150 to Station 2235 at SR 75)


East End (SR 75)

  • Jefferson County water line installation ongoing along SR75. BMPs installed by Jefferson County contractor.


Environmental Status this reporting period
:

  • 8 Rain Days: 6/1 (0.22”), 6/10 (0.27”), 6/12 (0.26”), 6/15 (0.07”), 6/20 (0.09”), 6/22 (0.33”), 6/26 (0.64”), 6/27 (1.18”),
  • Total rainfall for June was approximately 3.00 inches
  • No water quality violations.
  • ADEM Inspection June 15, 2015. No deficiencies noted.


 