Birmingham Northern Beltline - Better Beltline









Monthly Construction & Environmental Project Updates

May 2014


West End (Station 2137 at SR 79 to Station 2190)

  • Gas utility contractor relocation work ongoing near SR 79 utilizing both open trench and directional bore methods of installation.
  • Utility construction-related traffic control and water quality protection present.
  • No clearing or roadway construction activities have taken place on West End.


East End (Station 2200 to Station 2235 at SR 75)  


Environmental Status this reporting period:

  • 7 Rain Days: May 9 (0.22”), May 10 (0.12”), May 14 (1.11”), May 17 (0.10”), May 18 (0.39) May 28 (0.10’), May 29 (1.08”)
  • Total rainfall approximately 3.12”
  • No water quality violations this month.




 